Landmark Lehi Hospital

Intermountain Healthcare's latest PCH project is a critical healthcare project for a burgeoning population in Lehi and the greater Utah County area. 
By Milt Harrison

Since its inception more than a century ago in 1922, Primary Children's Hospital has set a standard for pediatric healthcare excellence by continuing to produce world-class facilities throughout the Beehive State. 

The latest cutting-edge offering is the Intermountain Primary Children's Hospital, Larry H. & Gail Miller Family Campus in Lehi (PCH Lehi), a project of significant importance to this burgeoning city, one that ranks among Utah's fastest-growing communities. 

Aided by a $50 million gift from the Miller Family Foundation, this landmark five-story, 486,000 SF, 66-bed project features the latest and greatest in medical technology in a building that is fun, playful, and energetic, with colorful design elements playing a vital aesthetic role throughout. The value of a project on this level is beyond measure, said Blake Court, Vice President of Salt Lake-based Jacobsen Construction. 

"Primary Children's really has a special place in my heart—they are a very special entity," said Court, a veteran healthcare professional with nearly 35 years of overall experience, including 19 years at Jacobsen along with stints at the State of Utah Division of Facilities Construction and Management and the Department of Veteran's Affairs. "It has been embraced by the community. Lehi and the surrounding areas are growing so fast. It's just amazing to see what's going on there." 

"It's a once-in-a-lifetime project," said Jeff Pinegar, Principal with Salt Lake-based VCBO Architecture, who partnered with Page Southerland Page of Houston on an exhaustive 19-month detailed planning and design process to create a comprehensive hospital and clinic in one congruous structure. "To see these kids have the spirit they have [...] it's a life-changing project. I'm so glad I had the chance to be part of it. I love the challenge of healthcare."

As with most construction projects that originated during the pandemic, PCH Lehi kicked off in August 2020, which proved immensely challenging from the onset in regard to worker health and volatility of material cost and availability. 

"Everyone knows the story—people got sick, it spread to co-workers, and we would lose entire crews [of subcontractors]," said Court. "We would constantly be down manpower. And then [material] lead times just skyrocketed. Materials that we normally get off the shelf went to a year-and-a-half overnight because manufacturing plants were shutting down. Add in price escalations and it was just a trifecta." 

(photo by Dana Sohm, Sohm Photografx) 

Community-Driven Project Serves a Huge Need 

During a ribbon-cutting ceremony a week before the facility officially opened on February 12, executives from Intermountain and Gail Miller spoke about the hospital's long-term impact.


“It’s been nearly four years that we announced the second campus of Primary Children’s Hospital, and we’ve all been anxiously awaiting the moment we open the doors to serve the children and families in the rapidly growing southern Salt Lake County and Utah County,” said Lisa Paletta, President of Intermountain Primary Children’s Hospital. “Together, everyone involved in the new campus has given life to our vision for a beautiful, healing space for children, and we are proud to celebrate this historical moment with you."


The Miller Family Campus is one part of Intermountain Health’s Primary Promise to build the nation’s model health system for children. It's a transformative, multi-layered plan with a minimum investment of $600 million in children’s health, shared by Intermountain Health and community philanthropic support.


The Primary Promise campaign was announced in January 2020 and boosted by the $50 million gift from the Larry H. & Gail Miller Family Foundation, the largest single investment in Miller family history.


“As Primary Children’s is guided by its philosophy, ‘The Child First and Always,’ our family is guided by the principle to ‘go about doing good until there is too much good in the world,’” said Gail Miller. “Our children have been helped by Primary Children’s in our hour of need, just like so many families before and after us. We are happy to support the good that Primary Children’s can do for children and families with this second location, and the Primary Promise vision to make the Intermountain West the home of the nation’s healthiest pediatric population."


Another major donation of $35 million was made to the Miller Family Campus by Todd Pedersen, Founder and former CEO of Vivint, Inc., who remarked “Gail is a shining example of the impact of giving back, and what’s possible for our children now and in generations to come.


I’m grateful to her and the many others here today who have followed in her footsteps and given generously to this hospital and Primary Promise.” Pedersen added, “Just think of what the future may hold when even more of us catch the vision and come together around this compelling cause of helping kids. We are close to $600 million, and my hope for everyone throughout this region is that they will be a part of history through this incredible project. Now is the time.”


Nearly 1,000 patients, caregivers, and Primary Promise supporters joined the Pedersen and Miller families at the special dedication ceremony, sharing in the awe and excitement expressed by Rob Allen, President and Chief Executive Officer of Intermountain Health.


“Today, more than ever, I feel as if we’re standing on the shoulders of giants,” Allen said. “Community support for the model health system for children is building. The power of philanthropy is what’s made Primary Children’s the beacon it has become – and will continue to fuel endless possibilities for children’s health.” 

Gary Krutsch, Project Manager for Jacobsen Construction, echoed the special nature of this project for those involved with the design and construction process. 

"I think about all of us on this project who have had a child, grandchild, or someone they love who has relied on the services of Primary Children's," said Krutsch. "That was a big reason why it was so special to be a part of this." 

Playful shapes, vibrant colors, and lively furniture and fixtures are essential components of helping children and their families feel comfortable throughout the hospital. (photos courtesy Jacobsen Construction; and  Midwest Commercial Interiors) 

Optimum Form and FunctionCreate a Dynamic Final Building

Pinegar said the design team, including professionals from VCBO and Intermountain Healthcare, visited a children's hospital in Seattle, one in Florida, and one at Stanford University to gain inspiration. One of the goals is to provide "a positive distraction" for children undergoing grueling medical procedures, which explains the vibrant, lively colors, sculptures of animals, and creative spaces for families. 


Functionally, Pinegar said they designed new room standards with separate areas for patients and doctors, places for nurses’ stations within specific units, new headwalls, and unique color palettes with diverse material offerings. 


The campus itself is designed as a supportive environment, offering quaint family spaces, childcare, and a park for all abilities, reflecting a focus on children. The exterior is highlighted with a bold, curved glass curtain wall system, making it a real showstopper. 


"What really stands out to me is the glass wave along the front of the building," said Krutsch. "It's an absolutely beautiful feature."


Interior spaces include state-of-the-art furniture and fixtures, with Salt Lake-based Midwest Commercial Interiors (MWCI) working closely with the architectural team to implement their vision and furniture specifications. MWCI programmed directly with each hospital department to ensure accuracy, while positively impacting patientcare, wayfinding, safety, operational needs, and strict environmental/cleaning protocols.


"The phasing and sequencing of the installation of a furniture package in a facility of this size is a well-orchestrated effort with many stakeholders and complex activities coordinated between trades and internal departments," said Sean Wright, President, MWCI/Midwest D-Vision Solutions. 


Sustainability is always a hallmark of healthcare facilities, and this hospital is aiming for LEED Silver certification, a baseline standard for Intermountain projects. 


Pinegar credited Carlos Linan, VCBO's Medical Equipment Planner, for his role in ensuring all new equipment and technology is factored into the design, which can be significantly altered by massive medical machines that require accurate floor plans. 


"[Carlos] is one of the best equipment planners in Utah—he knows all the equipment and makes changes to coordinate with those vendors. It's really complicated, with thousands of pieces of equipment to account for." 


Structurally, the project consists of steel beams and columns supporting concrete over steel deck floor and roof slabs, according to Clayton Burningham, Associate at Salt Lake-based Reaveley Engineers. The main lateral force resisting system is a bolted SidePlate moment frame, which allows for open bays and floor plans while maximizing program space and future flexibility. 


Egress stairs on the ends of the building are supported by tube steel moment frames, which facilitated an expression of the structure within the glass enclosure. The two monumental stairs are also of structural note as they cantilever off the edge of the floor slabs, with the only point of support being at each floor. This floating stair design kept the lobby atriums free from additional columns, opening up sight lines and helping the architectural team to achieve its vision for the main vertical thoroughfares of the hospital and clinic space. 


Court said this hospital ranks among his all-time favorite projects, which is notable given that he has participated in the construction of 29 major healthcare projects during his career. The challenges associated with these technical projects are not for the faint of heart.


"It's not just the importance of these projects—there is nothing harder to build than a hospital," said Court, checking off myriad critical equipment needs items like MRI, CTs, imaging machines, life support systems, etc. Building a children's hospital offers even more stringent requirements associated with security, along with robust backup power generators. He's seen incredible progress the past three-plus decades, and he's always impressed with how quickly technological advances are made in the healthcare industry, which spurs advances in construction techniques. 


"It's amazing what technology is doing today," said Court. "Structural systems continue to evolve; we're learning how to build things stronger and lighter. It's interesting [...] when I think we've reached the edge of something technological, somebody figures out how to push the envelope again." 


Quick Facts about PCH Lehi

Building weight: 69 million lbs. 

Peak workforce: 300-plus

Concrete: 23,000 CY

Cabling: 2 million LF (378 miles)

Paint: 11,000 gallons 


Inpatient Center includes:

Behavioral health unit with full services.

Walk-in pediatric behavioral crisis center.

19-bay emergency department and trauma services.

Neonatal intensive care (NICU) surgical services.

Pediatric intensive care (ICU) services.

Acute medical and surgical services.

Five operating suites.

Outpatient Center includes: 

Three behavioral health programs.

Diagnostic services and technology.

Safe and Healthy Families program.

Full outpatient rehab services.

Oncology and infusion center with a rooftop patio. 


Intermountain Primary Children's Hospital, 

Larry H. & Gail Miller Family Campus

Location: Lehi 

Owner: Intermountain Healthcare


Design Team

Architect: VCBO Architecture; Page Southerland Page

Civil Engineer: Great Basin Engineering
Electrical Engineer:
Spectrum Engineers
Mechanical Engineer:
VBFA
Structural Engineer:
Reaveley Engineers

Geotech: AGEC
Interior Design:
  VCBO Architecture
Landscape Architect:
ArcSitio Design


Construction Team

General Contractor: Jacobsen Construction Company

Concrete: Gene Peterson Concrete

Plumbing: J&S Mechanical

HVAC: J&S Mechanical; Palmer Christensen Co.             

Electrical: Taylor Electric, Cache Valley Electric

Masonry: IMS Masonry         

Drywall: DAW Construction Group

Painting: RP Painting & Decorating   

Tile/Stone: Millcreek Tile & Stone

Flooring: Jacobsen Flooring Services

Glazing/Curtain Wall: Flynn BEC

Steel Fabrication: SME Steel

Steel Erection: SME Steel (primary); Glassey Steel Works

Other Specialty Contractors: Guaranteed Waterproofing & Construction, B&B Excavating, Intermountain Plantings LLC, Rooftop Anchor, ISEC


By UC&D August 1, 2025
Nathan Goodrich
By Brad Fullmer August 1, 2025
Paul founded Paulsen Construction in 1925 after immigrating from Norway 16 years prior. Sprague Library in Sugar House was originally built by Paul, and then restored nearly 100 years later, led by current President John Paulsen.
By Utah C&D August 1, 2025
West Valley City Veteran’s Memorial Expansion Owner: West Valley City Architect: EDA Architects GC: Okland Construction Estimated Completion Date: September 2025
By Taylor Larsen August 1, 2025
Commercial office is not dead. The market is alive and well, according to the design pros at HB Workplaces team. Their new office and showroom in Draper, and what it has done for employees and clients, is a case in point. All it took was a change in scenery. Transitioning from the B'Nai Israel Temple, built in 1890, to a new space was a welcome change for the team. "I just remember working between 2015 and 2020, and it was just," Keilian Meyer trailed off as he described the former office, a historic religious building converted into an office and showroom in 1987. Minimal natural lighting, rooms and layouts misaligned for team needs—their space wasn't bringing out anyone's best work. Meyer, Marketing Director for HB Workplaces, said going to work didn't engender a sense of engagement. "It was kind of punch in and punch out." But everything coalesced with their move. "The timing aligned perfectly," Meyer said of the June 2024 move and their rebrand from the year before from Henriksen/Butler to HB Workplaces. Dual Purposes Come to Life It aligned with every real estate broker's favorite word: location. Planting the HB Workplaces flag in the award-winning Baltic Pointe made perfect sense, especially with its epicenter locale between the booming economies of Salt Lake and Utah counties. HB Workplaces CEO Dave Colling summed it all up succinctly: "Our new headquarters is not just another building; it's a statement of our appreciation and stewardship of design, built upon decades-long heritage of our own, along with MillerKnoll, underscoring our commitment to excellence." The mass timber ceilings in HB Workplaces' first-floor office in Baltic Pointe—the first of their kind for a commercial building in Utah—are part of that commitment. Everything seems warmer, healthier, and better under the all-lumber ceiling. "We've always been drawn to inspiring architecture, and the natural warmth and intentionality of this structure made it a natural fit," said Meyer. HB Workplaces sought to make their mass timber home a showpiece for the beautiful and wide-ranging possibilities of today's commercial interiors, serving as an office for the HB Workplaces team and a showroom for interior designers and architects looking to envision their next project. That dual nature comes through perfectly across the space, with the showroom piece especially highlighted in the "Living Room" and its 382 SF of mid-century modern glory. The unforgettable Eames Lounge chair catches the eye, but closer inspection reveals some nods to the B'Nai Israel Temple's stained glass windows and other homages to the deep histories of the Herman Miller and Knoll brands. The room's mid-century-style lounge chairs, couches, ottomans, and side tables—all MillerKnoll line, of course—combine with gentle lighting to create the perfect spot for hosting. Brit Badger, HB Workplaces' VP of Client Development, explained how the Living Room is ideal for getting to know their design partners and clients, especially for a first meeting. "It's not all the same seating everywhere, like it would be at a conference room," she explained of how the varied seating choices—the Nelson Coconut Lounge Chair is often first dibs—help to create a relaxed and comfortable environment. "It's cool to see who chooses what. It's a fun way to start."
By Brad Fullmer August 1, 2025
Bragging about a “C+” might seem gauche, but Utah is one of only four states to earn that high a grade, according to the May 28 release by the Utah Section of the American Society of Civil Engineers (ASCE) of the 2025 Report Card for Utah’s Infrastructure. The cumulative “C+” for the Beehive State is the highest mark ever given by ASCE to any individual state—the report card itself spans 12 categories of infrastructure and is virtually unchanged from 2020 (ASCE issues report cards every four years). Utah's grade is also one step higher than the national infrastructure average grade of “C” in the ASCE 2025 Report Card for America’s Infrastructure, which dropped in March. Roads (B+) and Bridges (B) remain the stars of the class, as the Utah Department of Transportation (UDOT) continues to receive consistent state funding in furthering its aggressive program of building new projects to meet ongoing demand, while diligently maintaining existing infrastructure. “Our transit and transportation are doing fabulous," said Anna Lisonbee, President of ASCE Utah and an Engineer-in-Training at South Jordan-based Hansen, Allen & Luce. “UDOT and UTA are lauded as some of the most efficient [organizations] nationwide, so we’re doing very well in that category.” Aviation infrastructure was the only category to see a grade increase—somewhat predictable given the sheer amount of capital investment made over the past decade at Salt Lake International Airport, Provo Airport, and other regional airports statewide. Three categories—bridges, s tormwater, and transit—saw grade decreases. The remaining eight categories held steady from 2020. "Utah is one of the fastest-growing states in the country, and state leaders have taken steps to ensure the reliability of infrastructure systems as more people move here to enjoy Utah's thriving communities, amazing outdoors, and high quality of life," said Craig Friant, Utah Civil Practice Lead for South Jordan-based Wilson & Company and Chair of the 2025 Report Card for Utah's Infrastructure. Utah grades per category: Roads: B+ Bridges: B Drinking Water, Solid Waste, Transit: B- Aviation, Dams, Hazardous Waste: C+ Stormwater, Wastewater: C Canals: D+ Levees: D-
By Taylor Larsen August 1, 2025
"What gets you out of Egypt doesn't take you to the promised land." The quote, as I first heard it, came from Ron Dunn, Founder of Salt Lake structural engineering firm Dunn Associates. While he was talking about the differences between founding and growing a company, the same principle holds true in developing a robust transportation infrastructure. In other words: "What got us here will not take us there." What has taken us here has been development dedicated to personal vehicles and last-mile freight—a stellar network of roads and highways from massive investments in horizontal construction. But what will get us "there" to the promised land? What will bring us to a future where Utahns can have the freedom to move without a car? Unified Plan for a Connected Utah? We'll certainly wander in the West Desert without a plan. Lucky us, we have hundreds of agreed-upon proposals across metropolitan planning organizations, cities and towns, counties, and even the Utah Department of Transportation. The Beehive State's guiding document toward long-term transportation plans, whether for cars or not, is found in the Utah Unified Transportation Plan, also known as the Unified Plan. The visionary document aims to prioritize funding across multiple transportation options and give residents choices, ranging from personal vehicles to mass transit and active transportation. Residents and metropolitan planning organizations across the state have added their input to further unify the state's trajectory. Key in Utah's Unified Plan, as documented, is analyzing and ultimately determining how transportation projects in Utah should be funded between 2023 - 2050. With projected needs across that timeline estimated at $153 billion in today's dollars, current revenue sources generating just under a projected $95 billion, and future revenue streams projected to generate just over $18 billion, we're going to be short. But where is that money going? Most often, it's funding roads. According to the Unified Plan, transportation needs from road capacity, maintenance, preservation, and operations project at a whopping $110 billion between 2023 - 2050, with a $29 billion funding gap in revenue. Funding future mass transit capacity ($14.8 billion) and operations ($19.8 billion) over the next 25 years costs a fraction of the projected costs for roads and highways. It's an apples-to-oranges comparison, admittedly, as massive funding for highways and freeways has created so much, but where do state priorities lead? Budget at a Glance Utah continues to tread the asphalt and concrete highway to prioritize highway funding. UDOT's FY2026 funding document shows $2.5 billion in funding. Estimated Transportation Investment Fund (TIF) expenditures, primarily used for improving or optimizing capacity, are projected at $1.2 billion. Within the TIF, Class B & Class C Roads, county roads and city streets, respectively, will receive $261 million, Highway Systems Construction $205 million, and Operations/Maintenance $254 million. It makes sense when $883 million in projected revenue for FY2026 comes from user-based fees, permits, and gas tax revenues (set to be 40 cents per gallon in 2026). On the other hand, UDOT-funded mass transit receives a bulk of its budget from the above-mentioned Transportation Investment Fund—35% of the index fuel tax sales tax goes into the Transit Transportation Investment Fund. For FY2026, transit and commuter rail projects will receive $103 million. John Gleason, UDOT's Sr. Public Information Officer, said there is a major shift happening within UDOT over the last decade-plus to give some "gas" to other forms of transportation. "All transportation is important to us. For every project we undertake, we are looking at the different components across all modes—cars, transit, bikes, trails," Gleason said. "We need to keep an eye on how the entire transportation system can function across the state." The words and shift in priorities are welcome, but what "Keeps Utah Moving", will not be more highway lanes or highway construction that receives the lion's share of transportation funding. Utah highways, like those in so many other states, are the victims of induced demand. The phenomenon is a matter of economics. For vehicle transportation, each lane added, highway developed, or road widened helps to expand capacity on these newly modified transportation corridors. However, expanding capacity does not mean solving traffic concerns. While capacity expands, more people are "induced" to use these freshly expanded corridors, lanes fill back to capacity, and commutes return to their sluggish nature. This never-ending quest to meet our transportation needs is set to play out again on I-15. UDOT is set to add another lane on I-15 from Farmington to Salt Lake, and do so at a multi-billion-dollar price tag. Surely this lane will be "The One" that fixes the traffic problem on Utah's busiest transit corridor? Utah may still be adjusting to roundabouts, but will we ever get out of this circle?
By Brad Fullmer August 1, 2025
Standing atop the now-tallest building in Utah—the dynamic 451-foot, 680,000-SF Astra Tower in downtown Salt Lake City—Lance Shields was succinct in describing the otherworldly, 360-degree views available from the 41st-floor rooftop patio. “Pretty amazing, isn’t it?” mused Shields, a Principal with Salt Lake-based HKS Architects and one of a half-dozen architects on HKS’ team who contributed to the design of Astra Tower, which features 377 total units, two levels of penthouse suites, and more than 40,000-SF of top-shelf amenity space. Peering southeast to majestic views of the Wasatch Mountains, Shields referenced the striking cantilever structure gracing the building’s southeast corner—a concession that preserved the breathtaking view by eliminating what would have been a structural column. Adding this approximately $2 million change to the bottom line only further illustrated the owner’s desire for a world-class luxury apartment tower. “The uninterrupted views of the valley are really breathtaking at the top floor and is the one thing that visitors I have taken through the project consistently comment on as the best experience they have had,” said Shields, adding that it would have been easy to justify a column in that corner. “I have to hand it to the vision of our team and the owner to see the value of the views and taking steps to preserve it.” Indeed, Boston-headquartered Kensington Investment Company (KIC) had been eyeing the Salt Lake market since 2017, ready to make a splash. In 2018, it purchased the site once home to Carl’s Jr. and hired HKS in 2019 to get the ball rolling on the design side. The pandemic forced KIC to pause its timeline, with construction formally kicking off in January 2022, led by Salt Lake-based Jacobsen Construction. “We were taking an enormous risk and writing a massive check while making sure we had as many people with experience on our team as we practically could,” said Ed Lewis, CEO of KIC. “We asked ourselves if Salt Lake City was ready for this kind of product—with no [like-building comparisons] to look to—while making the project financially successful. Putting together the capital stack with no comps in the state, and ensuring the team knew what they were doing, was challenging.” Engagement with the community was a priority from the start, said Shane Rensmon, President of Real Estate Development for KIC, as was finding local A/E/C firms with the moxie to take on a unique hybrid design-build project of this magnitude, a delivery method “not common in Salt Lake City, but common across major markets,” he said. “Ownership wanted to utilize local consultants and vendors as much as possible to get the community involved and engaged with the project, which presented new challenges in designing and constructing Astra Tower,” said Rensmon. “We leveraged [KIC’s] skills and experiences to help guide the design and construction teams on issues that they have not seen before or had little to no experience in.” Hotel-like Vibe with Unmatched Amenities Emir Tursic is no stranger to massive projects, having cut his teeth in the hospitality realm as a draftsman-turned-project architect for HKS on Block A of the enormous $10 billion MGM City Center project in Las Vegas from 2007-2008, which included the 61-story, 600,000-SF Aria Hotel. “It was a project I grew up very quickly with,” recalled Tursic, Office Director for HKS’ Salt Lake office, who ended up managing part of the project before it ended. “After this, I could go to the moon and not be scared of anything.” Even amidst the challenges for Tursic and his team, Astra Tower proved to be one of the most exciting, generational opportunities in the realm of world-class residential high-rise design that—ho-hum—also sets a record as the state’s tallest-ever building. “We wanted to create a sustainable urban community that focuses on wellness and sustainability,” said Tursic. “Sustainability is not just about energy and carbon footprint, it’s also [about] health and wellness and the environment. We have this huge amenity program—40,000 SF of indoor and outdoor amenities space focused on physical and mental health.” Tursic said dispersing major amenities across three building levels was a key functional design consideration. Level 8 kicks things off with an expansive club lounge that includes a demonstration kitchen and entertainment area, a state-of-the-art fitness center where views overlook Gallivan Plaza, a remote office space with a conference room and meeting rooms, and what Tursic calls “The bonus space”—an expansive 10,000 SF outdoor urban park. “Instead of a roof on top of the eight-story parking structure, we created a space with an outdoor lawn, hammocks, fire pits, grills—it’s a great social space for Astra’s residential community,” he said. Level 23 includes the outdoor pool and indoor spa, highlighted by a wellness center, steam room, sauna, recovery spas, treatment rooms, and private locker rooms. The pool deck overlook offers excellent views of the Oquirrh Mountains to the west. Level 41 tops the amenity spaces—literally—with an outdoor kitchen, entertainment area, and a spacious outdoor viewing deck that looks down on Salt Lake’s adjacent tallest buildings. “We wanted to provide a variety of experiences,” said Tursic. “The 41st floor is meant for quiet and solitude.” ROAM Interior Design of Los Angeles provided interior design on every level. "With Astra Tower, we set out to design interiors that reflect both the soul and natural beauty of Utah, infused with the energy of modern city living," said Deanne Teeter, Design Director at ROAM. “Every amenity—from the tranquil spa on the 23rd floor to the rooftop lounge with panoramic views—is intentionally crafted to foster wellness through biophilic connection and a true sense of home in the sky." “Astra Tower was purposefully designed to exemplify KIC's commitment to o perating market-leading apartment buildings, featuring state-of-the-art amenities and an unwavering dedication to service excellence,” said Joe Bird, Vice President of Real Estate Development for KIC. “This intentional design ensures an unparalleled living experience, blending sophisticated facilities with exceptional resident-focused service to set a new standard for urban residential excellence in Utah.”
By Brad Fullmer August 1, 2025
Ralph L. Wadsworth watches demolition activity on the I-80/1300 East Bridge Slide in August 2023 with granddaughter, Bradynn Wadsworth (Tod’s daughter), illustrating his genuine passion for construction. (all photos courtesy RLW Construction)
By Taylor Larsen August 1, 2025
First. Best. Leader. These are some of the many positive ways people described the late Marshall White, the civic hero and namesake of Ogden's past and future community centers. Marshall White is remembered as the first black police officer in Utah killed in the line of duty after being fatally shot in 1963. Equally important was his dedication to other causes outside of police work: the loving father of seven children; veteran and military doctor who helped establish a clinic at Hill Air Force Base post-WWII; youth mentor who partnered with the Elk's Club to establish the Wall Avenue Recreation Center; President of the Ogden chapter of the National Association for the Advancement of Colored People. Marshall White embodied community, and the original Marshall White Community Center, constructed five years after he died in 1968, was its physical manifestation. The building became a safe haven for youth, especially those with darker skin and different ethnicities from those of Utah "pioneer" ancestry, to learn to swim, take art classes, and participate in sports. But as time passed, the building fell into disrepair as Ogden's population shrank from the 1970s through the 1980s. Structural issues in the building appeared before a crack in the pool grew into a metaphorical chasm as COVID and its effects further disconnected society. Ogden needed champions who would follow in White's footsteps to bring people together, and create a space that would continue his community-building legacy. New Center; Relit Community Beacon Salt Lake-based VCBO was hired in 2020 to evaluate the old facility and propose future alternatives. It began, as VCBO Principal Brent Tippets described, "to replace a failing pool and building. […] It quickly became apparent that this community revolved around the Marshall N. White Community Center as both a gathering space and a historical icon for all minorities and people of humble circumstances." "Budget is always a challenge, but perhaps meeting all the affected parties' expectations was more so," said Tippets. "What was originally a pool and gymnasium replacement became a versatile destination with a plethora of participation options. He and the VCBO team worked with an Ogden City-appointed steering committee of passionate residents who provided valuable input on the importance and utilization of recreation and community spaces. "The Mayor, City Council, and City administration were committed to funding the project at the required level to achieve the grander vision for the facility," said Tippets. The Ogden City Council initially set aside $18 million and later increased the budget to $32 million for a new, 68,900-SF community building, doubling the size of the previous structure. Construction Challenges But challenges arose as soon as excavation commenced. Construction teams led by Vernal-based BHI encountered a dark, organic-looking soil that was previously undiscovered in geotechnical test borings. The surprise soil raised immediate concerns due to its lack of stability and reliability in compaction. BHI's history as an industrial contractor, where safety and lightning-fast communication are treasured, escalated the soil problems immediately. They collaborated and aligned with ownership, geotechnical engineers, and designers amidst evolving conditions to create a plan. Instead of utilizing native soils as initially planned, excavation teams removed the unsuitable material and imported structural fill from Ogden and nearby Plain City to meet compaction and bearing requirements, all while maintaining oh-so-important project momentum. "Working with Ogden City involved a different set of communication and coordination protocols than our typical projects," said BHI Superintendent Scot Marrot. "There was a greater emphasis on public transparency and adherence to specific city regulations. However, it was incredibly fulfilling to collaborate with the city officials who were passionate about providing a valuable resource for their community. The partnership fostered a strong sense of shared purpose and pride in the final outcome."
By Taylor Larsen August 1, 2025
Thoughtful consideration on Oquirrh Lake transformed the initial idea for the water feature into a community and ecological asset. The 67-acre lake weaves around the 130-acre recreation space, residential area, and wildlife habitat. (Main rendering and photo pictured courtesy LHM)