The Vue at Desert Color
Location: St George
Start/Completion: December 2023/June 2025
Cost: $41 million
Delivery Method: Design-Build/Assist
Stories/Levels: Four 3-story Apartment buildings, 1-story clubhouse
Project Team
Owner: PEG Companies, Woodbury Corporation, Desert Color
Design Team
Architect: Beecher Walker
Civil Engineer: Bush & Gudgell
Electrical Engineer: Hunt Electric
Mechanical Engineer: Shakespeare Engineering
Structural Engineer: Dunn Associates
Geotechnical Engineer: AGEC
Interior Design: KJ Designs
Landscape Architect: John Costanza
Construction Team
General Contractor: Layton Construction
Concrete: MS Concrete
Plumbing: Tom’s Mechanical
HVAC: Ace Mechanical Contractors
Electrical: Hunt Electric
Masonry: BA Robinson Construction
Drywall: KYCO
Painting: Accent Painting
Tile/Stone: Mojave Home Center, Unique Custom Exteriors
Millwork: CP Build
Flooring: Mojave Home Center
Roofing: Skyline Roofing
Glazing/Curtain Wall: USI All Purpose Windows & Doors
Waterproofing: WeatherSealed Incorporated
Steel Fabrication: Fab-Tec
Steel Erection: Stark Welding
Excavation: Suncore Construction & Materials
Landscaping: Stratton & Brätt