The New SLC Rolls On

The recent completion of Phase III includes the Central Tunnel (River Tunnel) connecting Concourses A and B, and the impressive Concourse B Plaza—highlighted by the beloved original "World Map" floor from the old Terminal 1.
By Milton Harrison

The historic Salt Lake City Airport Redevelopment (the New SLC) project continues to roll on into its fourth—and final—phase, with a targeted finish in October 2026 and final delivery of 16 new gates in Concourse B that will allow it to serve 34 million passengers annually. 

At a whopping $5.135 billion, the New SLC marks the single largest project in Utah's history, with the Phase I grand opening in September 2020 the first of many project milestones. The New SLC also sports the distinction of being the first new hub airport in the U.S. built in the 21st century, making it one of the most modern, technologically advanced, and aesthetically pleasing airports in the world. 

Last October, the $458 million Phase III was delivered by the Holder/Big-D Construction Joint Venture (HDJV) team, highlighted by the dynamic new 1,175-foot Central Tunnel—dubbed the "River Tunnel" for its mesmerizing blue ceiling art installation that depicts a flowing river—along with the Concourse B Plaza. The new plaza features an extension of the popular canyon motif with new art installations and the remarkable preservation of the former airport’s iconic "World Map" terrazzo floor section originally installed in 1960. 

Mike Williams, Program Director for the New SLC, expressed his excitement at the completion of Phase III, saying it's the most significant project milestone since Phase I opened in 2020.

"This is really what I call the second transformation of the airport. The first was when we opened Phase I in the fall of 2020," said Williams, the veritable maestro of this Herculean, once-in-a-lifetime project. “[Phase III] is the one that ties it all together and makes it function as one cohesive airport."

Williams said it's been remarkable to see how this project has morphed since it was announced more than a dozen years ago. At that time, the scope called for constructing just a new Concourse A and landside facilities. When the pandemic hit in March 2020, a mere six months before the scheduled grand opening of Phase I, SLC Airport officials pivoted with the original program and called for Concourse B to be built as well, essentially adding Phase III and Phase IV and nearly doubling the program budget to exceed $5 billion. 

Having the same general contractor team (HDJV) and design team, led by San Francisco-based HOK, on all four phases allowed a more seamless expansion since the goal of building Concourse B was to have it look and function virtually the same as Concourse A. 

Bill Wyatt, Executive Director of Airports for Salt Lake City, has been involved since 2017 and praised all parties involved for the successful completion of three major phases thus far, and for continually trying to improve the construction process from phase to phase. 

"During Phase I, we had this constant barrage of issues," said Wyatt. "I'd go on these construction walks with Mike [Williams], and someone from [HDJV], and it was a constant series of decisions that had to be made. We fixed all of those little things so that almost none of those issues were in Phase III and Phase IV. It's kind of like rinse and repeat—they're going on 10 years of building gates, and they have it pretty well down by now." 

Wyatt agreed with Williams that Phase III is the essential functional piece tying the entire project together, with the Central Tunnel being a vital connector between the two new concourses. The Central Tunnel makes a strong statement with its unique aesthetics and general stress-free vibe—highlighted by a carefully curated music playlist designed to help visitors decompress from the stresses of traveling on their journey to Concourse B. 

"In some ways, other than the [Phase I] grand opening itself in 2020, the opening of Phase III is the most significant," said Wyatt. "It makes the airport flow and function so much more effectively. Prior to this, people had a hard time understanding how it was going to come together—the Central Tunnel and Plaza of Concourse B really bring that together. We're very happy with the end result, the art [...] everything about it is terrific."

"There has been a ton of excitement seeing the public's reaction to the Central Tunnel opening," added Jordan Cammack, Construction Director for the past two years for HDJV, and a former Project Manager and Senior Project Manager who has been on the job since construction began in July 2014. He praised the cohesiveness of the design and construction teams over the past 11 years and the ability to make changes without disrupting the schedule or budget. 

"It's been impressive to see how the architect and design teams came together and worked with us throughout the project," Cammack added. "It's been a great job—it's been like a family out here with all our team members, owner reps, and architects. We've seen families grow up. It's a pleasure to come to work with such great people for an extended period of time." 
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button

The River Tunnel's ceiling art installation plays off the popular "Canyons" art feature found in both Concourse A and Concourse B (photo copyright Gordon Huether + Partners 2024).  Concourse B is highlighted with a "Northern Lights" glass installation and the beloved "World Map" floor section which was originally installed in Terminal 1 in 1960 and miraulously preserved and reinstalled in Plaza 2.0.

River Tunnel, Plaza 2.0 Highlight Aesthetic Elements of Phase III 

Beyond the tunnel and new plaza, Phase III includes a dozen new retail, food, and beverage concessions, and five Delta Air Lines gates, along with new baggage handling systems. The River Tunnel is the undeniable star of this phase, beyond the fact that functionally it cuts the traveling distance from Concourse A to Concourse B in half. 


The ceiling art installation was designed by Napa, Calif.-based Gordon Heuther, the artist on all art installations throughout the SLC Airport Redevelopment, and plays off “The Canyon,” the eye-catching art installation in Concourse A. 


The River Tunnel installation is comprised of aluminum tubing wrapped in Tweave Duratech 570C fabric to create fins, with LED lighting projected on the fins in various shades of blue. The experience is made complete by a curated playlist of 109 songs Huether himself primarily came up with and pumped through a 150-speaker system in a manner that guarantees travelers will hear a number of songs, but never the same one twice, during the roughly 5-minute walk. 


"It was challenging," Huether said of winnowing down the playlist, which is on Spotify. "What I realized as I was starting to delve into it [...] there are so many brilliant [musical] artists, so much talent, so much beauty, so much inspiration. I tried to focus on things that had to do with nature, travel [...] that had to do with love, basically. Everything from John Coltrane to Willie Nelson—I was kind of all over the place."


At the grand opening last October, Huether relayed a priceless story Williams told him about watching a traveler descend the escalator down to the River Tunnel the morning it opened, and upon hearing the first strains of music—Marvin Gaye's “Ain't No Mountain High Enough”—immediately threw her hands in the air and started dancing.


"Why does art in an airport matter?" Huether mused. "Art has the ability to reduce the stress of travel; art elevates the human spirit."


The River Tunnel also houses two cells, located on both sides of the pedestrian cell, for a future Automatic People Mover (passenger train) that could conceivably connect to a future Concourse C. 


Art is prominently featured throughout the Concourse B Plaza, or Plaza 2.0, as it carries similar themes from Concourse A art installations, including another canyon display, along with a "Northern Lights" installation that mirrors "The Falls"—a 50-foot-tall display of sparkling dichroic glass in Concourse A—albeit on a smaller scale. A replica fossil skeleton of Utah's state dinosaur, Ally the Allosaurus, was donated by the Natural History Museum of Utah and sits at the south end of Plaza 2.0 and adds a fun visual element, while being located just outside a new 34,000-SF Delta Sky Club, slated to open this fall. 


Perhaps the most impressive feature of Plaza 2.0, beyond the large 45-foot-tall window that looks to the north and tremendously aids daylighting, is the preservation of the beloved World Map floor installation that was originally installed in Terminal 1 of the former airport in 1960. Airport and construction officials went to great lengths to save the floor, a remarkable feat of construction that came off flawlessly. 


Leon Nelson, a Vice President at Salt Lake-based Big-D Construction and Construction Director for the first nine years of the New SLC, said preserving the World Map was simply a remarkable accomplishment.


"We didn't think it could be saved," said Nelson. "We decided to cut it up and pull a piece out and see what we had. We cut it into various pieces, then did a mock-up to see how it would look. It all came together perfectly, like it had never been touched. We were all on board." 


"The World Map is special to many people, so the desire was to save it or at least components of it, but we didn't know until it came time to demolish Terminal 1 that it could be saved," Williams added. "It was cut up into 75 pieces that were numbered, put back together, and restored to look like one map again. A truly amazing process." 


LEED Gold Goal Illustrates Emphasis on Sustainability

Williams stressed the importance of sustainability as a core value of the New SLC Airport from day one, and the project was designed to aggressively pursue LEED Gold Certification on the entire redevelopment. Williams said major sustainable items all contributed to the cause,  including high-performance glazing, maximum use of daylighting, installation of energy-efficient mechanical, electrical, and lighting systems, water conservation, and a streamlined design of terminals and gates to maximize airplane fuel use all contribute to the cause. 


Mechanical systems use indirect-direct evaporative cooling to reduce AC loads while achieving 80% cooling savings over standard designs. An air handling unit system was paired with a displacement air system that is integrated into column covers, turning the structure into a conduit for conditioned air and reducing fan energy usage. 


Electrical system design focused on performance, reliability, operational ease, and energy efficiency, with LED fixtures throughout all spaces. Three 13.8 KV feeders ensure a higher level of reliability, while multiple UPS systems utilizing lithium-ion batteries were installed to ensure continuous operation of critical systems. 


Seismic performance objectives were tailored for each building and developed to respond to regional resilience and economic considerations for each component of the program. Ultimately, the airport design met demanding seismic criteria with steel moment frames and buckling restrained braced frames while maintaining long, clear spans for traveler movement and sweeping landscape views. 


Matt Needham, Director of Aviation and Transportation at HOK, said it's been "humbling" to work on a project of this magnitude, and expressed gratitude for all team members and their collective collaborative spirit, particularly local architecture and engineering firms who assisted HOK's vast team. 


"We intentionally wanted to use local consultants and have been working with them hand-in-hand," said Needham. 

With the final phase of construction on the SLC Airport Redevelopment well into high gear, Needham said "To see the light at the end of the tunnel is so gratifying [...] you remember so many things about the direction and various changes and working with the airport owner and Delta. It was so hard to give them what they wanted, but we did."


Phase IV has been underway for 18 months and includes a 16-gate expansion on the east side of Concourse B, along with nearly 25,000 SF of restaurant and retail space (15 food and beverage locations). Five gates will be delivered this October, with the final 11 gates coming online in October 2026. 


Needham said with 94 total gates once Phase IV is completed, the only airport that might even compare to the New SLC is a new international airport in Doha, Qatar. 


"The key is the right amount of room—it's a very efficient terminal design," said Needham, who has more than 30 years of experience in aviation design. "The concourses are wider towards the center nodes and skinnier at the ends because there are fewer people. Phase III is the widest section of (Concourse B); Phase IV will be narrower."


Needham praised Wyatt and Williams for their respective leadership, with the latter being a great day-to-day orchestrator of various tasks, while doing it in a quiet, unassuming—yet remarkably effective—manner. 


"Mike [Williams] has been the guy who connects us all," said Needham. "The design has to be done just in time for the schedule, with all gates activated at a certain time. He's very considerate about both the design intent, but also making sure things don't cost an arm and a leg. He's the master integrator of this project." 


Needham also spoke on the deliberate branding of Utah that is associated with the design of the New SLC Airport, so people know they're most definitely in the Beehive State. 


"One of the cool things about this airport is, often when you're a transfer passenger you don't know where you are. Here, we really showcased the mountains, we maximized views, also the slot canyon with warm copper tones—you know you're in Utah." 


He added: "It's just really cool to think we had the opportunity to work on a project that impacts [26 million] people per year. It's humbling to realize that people you worked with have helped create a place that hopefully these millions of people can enjoy. The amount of people that have contributed to this project is incredible.


"You just don't get these opportunities; I'm very lucky. It's a once in a lifetime opportunity."


SLC Airport Redevelopment Phase III

Location: Salt Lake City

Start-Completion: November 2021-October 2024 

Cost: $458 million 

Delivery Method: CMAR

Square Footage: 338,562

Owner: Salt Lake City Department of Airports

Owner's Rep: Michael P. Williams


Design Team

Architect: HOK; MHTN Architects

Civil Engineer: HNTB

Electrical Engineer: HOK; Envision Engineering

Mechanical Engineer: HOK; Colvin Engineering

Structural Engineer: HOK; Dunn Associates, Inc.

Interior Design: HOK

Landscape Design: HOK; FFKR Architects

Geotech: RB&G

Baggage Handling Systems Design: Introba

Airfield/GSE/PBB design: AERO Systems Engineering


Construction Team 

General Contractor: Holder – Big-D, A Joint Venture (HDJV)

Concrete: Suntec Concrete

Plumbing & HVAC: J&S Mechanical

Electrical: Cache Valley Electric

Masonry: Allen’s Masonry Company

Tile/Stone: Superior Tile & Marble

Glazing / Metal Panels: Steel Encounters

Structure & Mis. Steel: SME Steel Contractors

Baggage Handling System: Vanderlande Industries

Doors / Frames/ Hardware: Midwest D-Vision Solutions

Apron Paving & Ground Improvements: Ralph L. Wadsworth Construction Company

Sitework: Ames Construction

Roofing: Flynn

Special Inspections / Testing: Terracon, GSH Material Testing & Inspections

Other Specialty Contractors: DAW Construction Group, ISEC, Wall 2 Wall Commercial Floorings, Keller North America, Specialty Systems, Fire Engineering Company, Kinley Construction Group, Schindler Elevator Company, Oshkosh Corporation, YESCO, M.C. Dean



By Bradley Fullmer April 30, 2026
The new St. George City Hall is a shining example of a collaborative process between owner, architect, and general contractor, producing a world-class facility that will serve the community for the next 40-plus years.  By Bradley Fullmer
By Bradley Fullmer April 30, 2026
After more than a half century designing buildings, 73-year-old Jim Child remains a fixture in Utah’s architectural community, with a genuine passion for his craft that inspires those around him.  By Bradley Fullmer
By Taylor Larsen April 30, 2026
Three Salt Lake City projects showcase the immense talent of the local A/E/C industry to achieve supreme levels of sustainability through adaptive reuse, turning drab offices into vibrant housing. By Taylor Larsen
By Taylor Larsen April 30, 2026
Design and construction teams working at “ludicrous” speeds delivered more than the Utah Mammoth’s new practice facilities, but also a fitting tribute to Utah’s strong hockey culture.
By Bradley Fullmer April 30, 2026
The passage of HB 355 in 2025 provided stability for Utah's construction aggregate producers. The question moving forward is: How long will the finite supply of materials last at existing operations along the Wasatch Front?
By B. Garn April 30, 2026
The new Deseret Peak High School delivers out-of-this-world design for a welcome addition to the growing Tooele Valley. 
By Taylor Larsen April 30, 2026
The eight-year odyssey to deliver Cyprus High was worth the voyage, as designers and builders created a stellar learning environment for Magna’s growing community.
By Taylor Larsen April 30, 2026
Engineers note the emerging trends among Utah’s different transit modes and how evolving technology and partnerships set the state up for success.  By Taylor Larsen
By Bradley Fullmer April 30, 2026
UC+D profiles four new firms who aim to make a name for themselves in an A/E/C market that refuses to slow down. By Bradley Fullmer
By Bradley Fullmer April 30, 2026
Led by the City of St. George, Washington County has experienced explosive growth of more than 50% over the past 15 years, ranking in the top 5% of all U.S. counties and fueling strong demand for commercial construction projects.  By Bradley Fullmer