Community First

The newly rebuilt Marshall N. White Community Center emerges as a best-in-class community center emphasizing flexibility and diversity throughout the building.
By Taylor Larsen

First. Best. Leader.


These are some of the many positive ways people described the late Marshall White, the civic hero and namesake of Ogden's past and future community centers. 


Marshall White is remembered as the first black police officer in Utah killed in the line of duty after being fatally shot in 1963. Equally important was his dedication to other causes outside of police work: the loving father of seven children; veteran and military doctor who helped establish a clinic at Hill Air Force Base post-WWII; youth mentor who partnered with the Elk's Club to establish the Wall Avenue Recreation Center; President of the Ogden chapter of the National Association for the Advancement of Colored People.


Marshall White embodied community, and the original Marshall White Community Center, constructed five years after he died in 1968, was its physical manifestation. The building became a safe haven for youth, especially those with darker skin and different ethnicities from those of Utah "pioneer" ancestry, to learn to swim, take art classes, and participate in sports. 


But as time passed, the building fell into disrepair as Ogden's population shrank from the 1970s through the 1980s. Structural issues in the building appeared before a crack in the pool grew into a metaphorical chasm as COVID and its effects further disconnected society.


Ogden needed champions who would follow in White's footsteps to bring people together, and create a space that would continue his community-building legacy.


New Center; Relit Community Beacon


Salt Lake-based VCBO was hired in 2020 to evaluate the old facility and propose future alternatives. It began, as VCBO Principal Brent Tippets described, "to replace a failing pool and building. […] It quickly became apparent that this community revolved around the Marshall N. White Community Center as both a gathering space and a historical icon for all minorities and people of humble circumstances." 


"Budget is always a challenge, but perhaps meeting all the affected parties' expectations was more so," said Tippets. "What was originally a pool and gymnasium replacement became a versatile destination with a plethora of participation options.


He and the VCBO team worked with an Ogden City-appointed steering committee of passionate residents who provided valuable input on the importance and utilization of recreation and community spaces. 


"The Mayor, City Council, and City administration were committed to funding the project at the required level to achieve the grander vision for the facility," said Tippets.


The Ogden City Council initially set aside $18 million and later increased the budget to $32 million for a new, 68,900-SF community building, doubling the size of the previous structure.


Construction Challenges


But challenges arose as soon as excavation commenced. Construction teams led by Vernal-based BHI encountered a dark, organic-looking soil that was previously undiscovered in geotechnical test borings. The surprise soil raised immediate concerns due to its lack of stability and reliability in compaction.


BHI's history as an industrial contractor, where safety and lightning-fast communication are treasured, escalated the soil problems immediately. They collaborated and aligned with ownership, geotechnical engineers, and designers amidst evolving conditions to create a plan. Instead of utilizing native soils as initially planned, excavation teams removed the unsuitable material and imported structural fill from Ogden and nearby Plain City to meet compaction and bearing requirements, all while maintaining oh-so-important project momentum. 


"Working with Ogden City involved a different set of communication and coordination protocols than our typical projects," said BHI Superintendent Scot Marrot. "There was a greater emphasis on public transparency and adherence to specific city regulations. However, it was incredibly fulfilling to collaborate with the city officials who were passionate about providing a valuable resource for their community. The partnership fostered a strong sense of shared purpose and pride in the final outcome."


  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button

Art in the Marshall N. White Community Center that depicts the life of Marshall White is seen at the facility entrance, and again in the hallway. The center has upgraded aquatic facilities, as well as an expansive weight room and elevated running track.

Activities for All


On the design side, both Tippets and Eric Peng, Project Manager at VCBO, said that design intent centered on flexibility and diversity of function. Designers envisioned the new center as accessible as possible for the community to host multiple types of activities.


"The City wanted a space to host various events and accommodate large gatherings," Peng said of how those desires manifested in the 3,600-SF community room. "But they also wanted the flexibility to split the space into smaller, more intimate rooms that could function as classrooms, conference rooms, dance studios, etc."


Two sets of movable walls open up the community room entirely, while roll-up doors allow for an even greater hosting component, where visitors can pass through those doors into the hallway and then into the gym. 


Those choices helped create an unforgettable opening day, as Peng described how it felt like all of Ogden showed up in support.


"The parking lot was packed with community members eager to tour and experience the facility," Peng said. "It was exciting to watch their interactions, showcasing the versatility of the space."


But much like the old building, this is more than a recreation center. Peng mentioned how many features from the old center are new and improved in the new facility. The Head Start program space for children is especially spacious, with massive windows bringing in a light and energy matched by the children who play there. The new ceramic studio is larger, too. It features pottery wheels, ample storage space, and a kiln for the emerging artisans of Ogden. On the other side of the wall from the ceramic studio is a full commercial kitchen designed, as Tippets described, "as a teaching kitchen to share cultural dishes and basic cooking skills."


Dipping into a New Pool


As Tippets mentioned, the indoor pool was a starting point in early programming conversations. The center's Myrtha pool system brought top-tier pool tech to Ogden. The stainless-steel prefabricated panels that form the pool structure were hot-rolled with a PVC laminate before being further bonded together with a PVC liquid that penetrates the joint between panels to create a superb seal and uniform finish across the 137,000-gallon pool.


To raise the standard of the pool facility, design called for an absolute jaw-dropper of a curtain wall on the building's west side. It stretches 116 feet across and 27 feet high, bringing in so much passive light to the pool that you'd be forgiven for thinking you're outside on a cloudy day. 


Marrot said the pool sits at a comfortable 86 degrees, while the air moving through the aquatic center is slightly warmer at 88 degrees, thanks to a massive RTU system. The Superintendent joked that the team working this scope performed "a true labor of love", punching out air intake holes by hand across 250 SF of composite wood slat siding. Their work is excellent—the wood slat air intake combines perfectly with the other walls to keep systems out of sight and out of mind for patrons. 


Athletics Remain Focal Point


Athletic facilities extend just past the locker rooms and continue the flexible design intent to meet diverse athletic needs. 


The 8,500-SF Nordic Oak basketball court features six hoops along with court markings for both basketball and pickleball. Dividers can drop from the ceiling to split the floor into two smaller courts for a future Damien Lillard or Tom Chambers to hoop it up. 


Further down the hall is the synthetic turf field set up for soccer and the next Michele Vasconcelos or Taylor Booth. The project team pointed out how the netting above the fieldhouse can drop down to form a half dozen batting cages for the next softball great, like Amy Hogue, or baseball legend, like Bill Buckner.


Up the stairs to the second level and one gains an appreciation for the resources devoted to nearly doubling the space of the new center.


"The goal, Tippets said, "was to create an enegetic, open, and inviting space […] that has visibility throughout the interior of the building.


Beyond an exercise studio for yoga, spin, barre, or other classes, free weights, machines, boxing equipment, and squat racks allow participants a wide range of workout options. The 10 millimeter-thick Mondo flooring, double thick in the boxing and squat rack areas, spans 12,000 SF across the gym and then out and around the floating track that circles the basketball court and indoor field.


As the building tour looked out over the fields from the track, Marrot detailed another challenge confronted by the construction team during erection of the steel joist just above. Discrepencies between shop drawings and fabricated joist thickness required field adjustments from the steel erector to ensure proper alignment and structural continuity. 


"Our team quickly adapted by reworking affected beams in coordination with the erector and structural engineer to minimize schedule delays and preserving design integrity," said Marrot. "The experience reinforced the importance of sharing finalized production details when available in projects with tight structural coordination zones."


Project Reaches Finish Line


Much like a diverse group can bring out the best of everyone, materials like the 13,500 SF of clay-faced and copper matte brick masonry, 39,000 CMU blocks, 13,700 SF of glazing, and others combine to create a diverse and gorgeous community center. The 145 metal panels near the entrance—in Ogden blue—work hand in hand with beautiful murals depicting the heroic life of Marshall White to add city-specific notes that live up to the legacy he started nearly a century ago.


But before the grand opening, the project partnership received one final test two months before the new community center wrapped up. 


"They didn't have it in their initial budget," said Peng of the additions, "but they received some grants that allowed us to polish off the final parts of the project."


The new scope included outdoor pickleball courts, a soccer field and perimeter fence. Beyond sporting amenities, construction teams also replaced the western sidewalk and installed an additional food truck pad on the eastern edge of the parking lot. These additions round out an incredibly diverse set of activities and features for patrons and Ogden City residents. 


"It was challenging," said Marrot of the 11th-hour additions. How challenging? It's hard to say, considering all the new features tie in so well with the community center that one would never know that it wasn't planned this way from the start. "But it was exciting to see that finished product be completely finished."


Ogden City representatives agreed. "The Marshall N. White Community Center is a space built for all of Ogden—especially our youth," said Edd Bridge, Recreation Director for Ogden City. "It reflects the city's commitment to providing a place for residents to come together, stay active, and grow—and it honors the legacy of Marshall White and what he stood for: service, opportunity, and community."


Much like its namesake, the Marshall N. White Community Center continues a legacy of bringing diverse people from across the area together to experience the joy of sport and community.

Marshall N. White Community Center

Location: Ogden

Cost: $33,000,000

Delivery Method: Lump Sum


Project Team

Owner: Ogden City

Owner’s Reps: Edd Bridge; Justin Anderson, Taylor Nielsen


Design Team

Architect: VCBO Architecture

Electrical Engineer: ECE Engineering

Mechanical Engineer: Heath Engineering Company

Structural Engineer: ARW Engineers

Civil Engineer: Great Basin Engineering

Landscape Architect: Prime Landscape Architecture

Geo-Technical: Ninyo & Moore

Pool Design: Water Design

Food Services: Jedrziewski Designs


Construction Team

General Contractor: BHI Co.

Concrete: Cornerstone Concrete

Plumbing: Advanced Plumbing & Mechanical

HVAC: Stellar Mechanical

Electrical: Ludvik Electric

Masonry: Allen’s Masonry Company

Drywall/Acoustics: HD Build

Painting: Painter Bros

Tile/Stone: Wall 2 Wall 

Carpentry: Cheney Brothers

Flooring: Wall 2 Wall; Comfloors

Roofing: Redd Roofing

Glass/Curtain Wall: Gordons Glass

Waterproofing: Rocky Mountain Waterproofing

Pool/Aquatic Features: CEM Aquatics

Steel Fabrication/Erection: Prestige Constructors

Excavation: Next Construction

Demolition: Perez Company

Precast: Allen’s Masonry Company

Landscaping: Modern X Landscaping




By UC&D August 1, 2025
Nathan Goodrich
By Brad Fullmer August 1, 2025
Paul founded Paulsen Construction in 1925 after immigrating from Norway 16 years prior. Sprague Library in Sugar House was originally built by Paul, and then restored nearly 100 years later, led by current President John Paulsen.
By Utah C&D August 1, 2025
West Valley City Veteran’s Memorial Expansion Owner: West Valley City Architect: EDA Architects GC: Okland Construction Estimated Completion Date: September 2025
By Taylor Larsen August 1, 2025
Commercial office is not dead. The market is alive and well, according to the design pros at HB Workplaces team. Their new office and showroom in Draper, and what it has done for employees and clients, is a case in point. All it took was a change in scenery. Transitioning from the B'Nai Israel Temple, built in 1890, to a new space was a welcome change for the team. "I just remember working between 2015 and 2020, and it was just," Keilian Meyer trailed off as he described the former office, a historic religious building converted into an office and showroom in 1987. Minimal natural lighting, rooms and layouts misaligned for team needs—their space wasn't bringing out anyone's best work. Meyer, Marketing Director for HB Workplaces, said going to work didn't engender a sense of engagement. "It was kind of punch in and punch out." But everything coalesced with their move. "The timing aligned perfectly," Meyer said of the June 2024 move and their rebrand from the year before from Henriksen/Butler to HB Workplaces. Dual Purposes Come to Life It aligned with every real estate broker's favorite word: location. Planting the HB Workplaces flag in the award-winning Baltic Pointe made perfect sense, especially with its epicenter locale between the booming economies of Salt Lake and Utah counties. HB Workplaces CEO Dave Colling summed it all up succinctly: "Our new headquarters is not just another building; it's a statement of our appreciation and stewardship of design, built upon decades-long heritage of our own, along with MillerKnoll, underscoring our commitment to excellence." The mass timber ceilings in HB Workplaces' first-floor office in Baltic Pointe—the first of their kind for a commercial building in Utah—are part of that commitment. Everything seems warmer, healthier, and better under the all-lumber ceiling. "We've always been drawn to inspiring architecture, and the natural warmth and intentionality of this structure made it a natural fit," said Meyer. HB Workplaces sought to make their mass timber home a showpiece for the beautiful and wide-ranging possibilities of today's commercial interiors, serving as an office for the HB Workplaces team and a showroom for interior designers and architects looking to envision their next project. That dual nature comes through perfectly across the space, with the showroom piece especially highlighted in the "Living Room" and its 382 SF of mid-century modern glory. The unforgettable Eames Lounge chair catches the eye, but closer inspection reveals some nods to the B'Nai Israel Temple's stained glass windows and other homages to the deep histories of the Herman Miller and Knoll brands. The room's mid-century-style lounge chairs, couches, ottomans, and side tables—all MillerKnoll line, of course—combine with gentle lighting to create the perfect spot for hosting. Brit Badger, HB Workplaces' VP of Client Development, explained how the Living Room is ideal for getting to know their design partners and clients, especially for a first meeting. "It's not all the same seating everywhere, like it would be at a conference room," she explained of how the varied seating choices—the Nelson Coconut Lounge Chair is often first dibs—help to create a relaxed and comfortable environment. "It's cool to see who chooses what. It's a fun way to start."
By Brad Fullmer August 1, 2025
Bragging about a “C+” might seem gauche, but Utah is one of only four states to earn that high a grade, according to the May 28 release by the Utah Section of the American Society of Civil Engineers (ASCE) of the 2025 Report Card for Utah’s Infrastructure. The cumulative “C+” for the Beehive State is the highest mark ever given by ASCE to any individual state—the report card itself spans 12 categories of infrastructure and is virtually unchanged from 2020 (ASCE issues report cards every four years). Utah's grade is also one step higher than the national infrastructure average grade of “C” in the ASCE 2025 Report Card for America’s Infrastructure, which dropped in March. Roads (B+) and Bridges (B) remain the stars of the class, as the Utah Department of Transportation (UDOT) continues to receive consistent state funding in furthering its aggressive program of building new projects to meet ongoing demand, while diligently maintaining existing infrastructure. “Our transit and transportation are doing fabulous," said Anna Lisonbee, President of ASCE Utah and an Engineer-in-Training at South Jordan-based Hansen, Allen & Luce. “UDOT and UTA are lauded as some of the most efficient [organizations] nationwide, so we’re doing very well in that category.” Aviation infrastructure was the only category to see a grade increase—somewhat predictable given the sheer amount of capital investment made over the past decade at Salt Lake International Airport, Provo Airport, and other regional airports statewide. Three categories—bridges, s tormwater, and transit—saw grade decreases. The remaining eight categories held steady from 2020. "Utah is one of the fastest-growing states in the country, and state leaders have taken steps to ensure the reliability of infrastructure systems as more people move here to enjoy Utah's thriving communities, amazing outdoors, and high quality of life," said Craig Friant, Utah Civil Practice Lead for South Jordan-based Wilson & Company and Chair of the 2025 Report Card for Utah's Infrastructure. Utah grades per category: Roads: B+ Bridges: B Drinking Water, Solid Waste, Transit: B- Aviation, Dams, Hazardous Waste: C+ Stormwater, Wastewater: C Canals: D+ Levees: D-
By Taylor Larsen August 1, 2025
"What gets you out of Egypt doesn't take you to the promised land." The quote, as I first heard it, came from Ron Dunn, Founder of Salt Lake structural engineering firm Dunn Associates. While he was talking about the differences between founding and growing a company, the same principle holds true in developing a robust transportation infrastructure. In other words: "What got us here will not take us there." What has taken us here has been development dedicated to personal vehicles and last-mile freight—a stellar network of roads and highways from massive investments in horizontal construction. But what will get us "there" to the promised land? What will bring us to a future where Utahns can have the freedom to move without a car? Unified Plan for a Connected Utah? We'll certainly wander in the West Desert without a plan. Lucky us, we have hundreds of agreed-upon proposals across metropolitan planning organizations, cities and towns, counties, and even the Utah Department of Transportation. The Beehive State's guiding document toward long-term transportation plans, whether for cars or not, is found in the Utah Unified Transportation Plan, also known as the Unified Plan. The visionary document aims to prioritize funding across multiple transportation options and give residents choices, ranging from personal vehicles to mass transit and active transportation. Residents and metropolitan planning organizations across the state have added their input to further unify the state's trajectory. Key in Utah's Unified Plan, as documented, is analyzing and ultimately determining how transportation projects in Utah should be funded between 2023 - 2050. With projected needs across that timeline estimated at $153 billion in today's dollars, current revenue sources generating just under a projected $95 billion, and future revenue streams projected to generate just over $18 billion, we're going to be short. But where is that money going? Most often, it's funding roads. According to the Unified Plan, transportation needs from road capacity, maintenance, preservation, and operations project at a whopping $110 billion between 2023 - 2050, with a $29 billion funding gap in revenue. Funding future mass transit capacity ($14.8 billion) and operations ($19.8 billion) over the next 25 years costs a fraction of the projected costs for roads and highways. It's an apples-to-oranges comparison, admittedly, as massive funding for highways and freeways has created so much, but where do state priorities lead? Budget at a Glance Utah continues to tread the asphalt and concrete highway to prioritize highway funding. UDOT's FY2026 funding document shows $2.5 billion in funding. Estimated Transportation Investment Fund (TIF) expenditures, primarily used for improving or optimizing capacity, are projected at $1.2 billion. Within the TIF, Class B & Class C Roads, county roads and city streets, respectively, will receive $261 million, Highway Systems Construction $205 million, and Operations/Maintenance $254 million. It makes sense when $883 million in projected revenue for FY2026 comes from user-based fees, permits, and gas tax revenues (set to be 40 cents per gallon in 2026). On the other hand, UDOT-funded mass transit receives a bulk of its budget from the above-mentioned Transportation Investment Fund—35% of the index fuel tax sales tax goes into the Transit Transportation Investment Fund. For FY2026, transit and commuter rail projects will receive $103 million. John Gleason, UDOT's Sr. Public Information Officer, said there is a major shift happening within UDOT over the last decade-plus to give some "gas" to other forms of transportation. "All transportation is important to us. For every project we undertake, we are looking at the different components across all modes—cars, transit, bikes, trails," Gleason said. "We need to keep an eye on how the entire transportation system can function across the state." The words and shift in priorities are welcome, but what "Keeps Utah Moving", will not be more highway lanes or highway construction that receives the lion's share of transportation funding. Utah highways, like those in so many other states, are the victims of induced demand. The phenomenon is a matter of economics. For vehicle transportation, each lane added, highway developed, or road widened helps to expand capacity on these newly modified transportation corridors. However, expanding capacity does not mean solving traffic concerns. While capacity expands, more people are "induced" to use these freshly expanded corridors, lanes fill back to capacity, and commutes return to their sluggish nature. This never-ending quest to meet our transportation needs is set to play out again on I-15. UDOT is set to add another lane on I-15 from Farmington to Salt Lake, and do so at a multi-billion-dollar price tag. Surely this lane will be "The One" that fixes the traffic problem on Utah's busiest transit corridor? Utah may still be adjusting to roundabouts, but will we ever get out of this circle?
By Brad Fullmer August 1, 2025
Standing atop the now-tallest building in Utah—the dynamic 451-foot, 680,000-SF Astra Tower in downtown Salt Lake City—Lance Shields was succinct in describing the otherworldly, 360-degree views available from the 41st-floor rooftop patio. “Pretty amazing, isn’t it?” mused Shields, a Principal with Salt Lake-based HKS Architects and one of a half-dozen architects on HKS’ team who contributed to the design of Astra Tower, which features 377 total units, two levels of penthouse suites, and more than 40,000-SF of top-shelf amenity space. Peering southeast to majestic views of the Wasatch Mountains, Shields referenced the striking cantilever structure gracing the building’s southeast corner—a concession that preserved the breathtaking view by eliminating what would have been a structural column. Adding this approximately $2 million change to the bottom line only further illustrated the owner’s desire for a world-class luxury apartment tower. “The uninterrupted views of the valley are really breathtaking at the top floor and is the one thing that visitors I have taken through the project consistently comment on as the best experience they have had,” said Shields, adding that it would have been easy to justify a column in that corner. “I have to hand it to the vision of our team and the owner to see the value of the views and taking steps to preserve it.” Indeed, Boston-headquartered Kensington Investment Company (KIC) had been eyeing the Salt Lake market since 2017, ready to make a splash. In 2018, it purchased the site once home to Carl’s Jr. and hired HKS in 2019 to get the ball rolling on the design side. The pandemic forced KIC to pause its timeline, with construction formally kicking off in January 2022, led by Salt Lake-based Jacobsen Construction. “We were taking an enormous risk and writing a massive check while making sure we had as many people with experience on our team as we practically could,” said Ed Lewis, CEO of KIC. “We asked ourselves if Salt Lake City was ready for this kind of product—with no [like-building comparisons] to look to—while making the project financially successful. Putting together the capital stack with no comps in the state, and ensuring the team knew what they were doing, was challenging.” Engagement with the community was a priority from the start, said Shane Rensmon, President of Real Estate Development for KIC, as was finding local A/E/C firms with the moxie to take on a unique hybrid design-build project of this magnitude, a delivery method “not common in Salt Lake City, but common across major markets,” he said. “Ownership wanted to utilize local consultants and vendors as much as possible to get the community involved and engaged with the project, which presented new challenges in designing and constructing Astra Tower,” said Rensmon. “We leveraged [KIC’s] skills and experiences to help guide the design and construction teams on issues that they have not seen before or had little to no experience in.” Hotel-like Vibe with Unmatched Amenities Emir Tursic is no stranger to massive projects, having cut his teeth in the hospitality realm as a draftsman-turned-project architect for HKS on Block A of the enormous $10 billion MGM City Center project in Las Vegas from 2007-2008, which included the 61-story, 600,000-SF Aria Hotel. “It was a project I grew up very quickly with,” recalled Tursic, Office Director for HKS’ Salt Lake office, who ended up managing part of the project before it ended. “After this, I could go to the moon and not be scared of anything.” Even amidst the challenges for Tursic and his team, Astra Tower proved to be one of the most exciting, generational opportunities in the realm of world-class residential high-rise design that—ho-hum—also sets a record as the state’s tallest-ever building. “We wanted to create a sustainable urban community that focuses on wellness and sustainability,” said Tursic. “Sustainability is not just about energy and carbon footprint, it’s also [about] health and wellness and the environment. We have this huge amenity program—40,000 SF of indoor and outdoor amenities space focused on physical and mental health.” Tursic said dispersing major amenities across three building levels was a key functional design consideration. Level 8 kicks things off with an expansive club lounge that includes a demonstration kitchen and entertainment area, a state-of-the-art fitness center where views overlook Gallivan Plaza, a remote office space with a conference room and meeting rooms, and what Tursic calls “The bonus space”—an expansive 10,000 SF outdoor urban park. “Instead of a roof on top of the eight-story parking structure, we created a space with an outdoor lawn, hammocks, fire pits, grills—it’s a great social space for Astra’s residential community,” he said. Level 23 includes the outdoor pool and indoor spa, highlighted by a wellness center, steam room, sauna, recovery spas, treatment rooms, and private locker rooms. The pool deck overlook offers excellent views of the Oquirrh Mountains to the west. Level 41 tops the amenity spaces—literally—with an outdoor kitchen, entertainment area, and a spacious outdoor viewing deck that looks down on Salt Lake’s adjacent tallest buildings. “We wanted to provide a variety of experiences,” said Tursic. “The 41st floor is meant for quiet and solitude.” ROAM Interior Design of Los Angeles provided interior design on every level. "With Astra Tower, we set out to design interiors that reflect both the soul and natural beauty of Utah, infused with the energy of modern city living," said Deanne Teeter, Design Director at ROAM. “Every amenity—from the tranquil spa on the 23rd floor to the rooftop lounge with panoramic views—is intentionally crafted to foster wellness through biophilic connection and a true sense of home in the sky." “Astra Tower was purposefully designed to exemplify KIC's commitment to o perating market-leading apartment buildings, featuring state-of-the-art amenities and an unwavering dedication to service excellence,” said Joe Bird, Vice President of Real Estate Development for KIC. “This intentional design ensures an unparalleled living experience, blending sophisticated facilities with exceptional resident-focused service to set a new standard for urban residential excellence in Utah.”
By Brad Fullmer August 1, 2025
Ralph L. Wadsworth watches demolition activity on the I-80/1300 East Bridge Slide in August 2023 with granddaughter, Bradynn Wadsworth (Tod’s daughter), illustrating his genuine passion for construction. (all photos courtesy RLW Construction)
By Taylor Larsen August 1, 2025
Thoughtful consideration on Oquirrh Lake transformed the initial idea for the water feature into a community and ecological asset. The 67-acre lake weaves around the 130-acre recreation space, residential area, and wildlife habitat. (Main rendering and photo pictured courtesy LHM)
By Taylor Larsen June 30, 2025
Not often does an opportunity come around to build a new state park. But the project team jumped at the chance and helped bring amenities to the off-roading wilderness around Moab to deliver the new Utahraptor State Park. The unique project received design collaboration from Johansen & Tuttle Engineering, GSBS Architects, Horrocks, and Spectrum Engineers. Hogan & Associates Construction led construction efforts to bring in site infrastructure, utilities, and vertical construction to build new recreation opportunities for Moab’s tourism hotbed. The project’s remote location made this a major challenge. Still, best-in-class coordination helped to mitigate labor concerns and site issues to build a fitting tribute to the area’s history as Utahraptor State Park prepares for its first summer tourist season in 2025. Designing a Fitting Park for the Area The park was created in 2021 via legislative action (H.B. 257), while the infrastructure and more began construction in 2023. The site is historic in two senses. It is home to ancient history, with fossil sites of the Utahraptor found throughout the area—fossils first discovered outside the Dalton Wells Quarry by paleontologist “Dinosaur Jim” Jensen in 1975. It is also an area of 20th-century history as the former site of the Dalton Wells Isolation Center, the Civilian Conservation Corps facility-turned-internment camp where Japanese Americans were detained from 1942-1945 during World War II. Owner’s representatives from the State of Utah’s Division of Facilities Construction and Management (DFCM) said an overall goal for Utah State Parks was to preserve these historic assets amidst steady and consistent tourist and recreation growth. According to Matt Boyer, Assistant Director of Capital Development for DFCM, Utahraptor State Park's development would happen “in a way that would preserve the historic nature of the site while maintaining the opportunity for recreation in the process.” According to Clio Rayner, Principal for GSBS, the design goal aimed to complement instead of compete with the natural beauty of the surrounding landscape. “We wanted to provide a subtle sense of arrival where people feel a sense of welcome and comfort,” she said. Design leaders wanted the harsh beauty and serenity of the Colorado Plateau Desert to remain the showstopper. “We went into this design not wanting to make an architectural statement but rather wanting to create a visitor experience focused on the landscape. In a place like this, it should not be about the architecture.” Since the built environment of Utahraptor State Park would consist of recreational facilities and a visitor center, Rayner explained, “We used a material palette and building massing that reflected natural features of the site and created flexible open interior space for multiple uses.” Interior design, said Rayner, “Provided an open opportunity for Utah Parks to create interpretive exhibits inside the Utahraptor visitor center that tell the story and convey the significance of the site.” Design incorporated economical and durable features like natural wood and CMU colors and patterns drawn from the stone features that abound in Utah's eastern majesty.