Goal!

There was a bit of déjà vu on the new UCCU Soccer Stadium project at UVU for a couple of members of the project team.
By Brad Fullmer

 Front view of the bleachers, press box, and suites. (photos courtesy SIRQ Construction)

This is paragraph text. Click it or hit the Manage Text button to change the font, color, size, format, and more. To set up site-wide paragraph and title styles, go to Site Theme.

For Erik Dunn, overseeing the construction of the new UCCU Soccer Stadium at Utah Valley University was a true "full-circle moment" for him, given that he played soccer at UVU (then Utah Valley State College) for two seasons in 1997-98.


"I'm looking at the field I tried out on," said Dunn, Project Executive for Lehi-based SIRQ Construction, during a phone interview three weeks after the ribbon cutting August 15 of the $21  million project. "When this popped up on the radar, I knew I had to chase this one. It was one of those (feelings of) 'this has got to be my job!'" 


Dunn's genuine passion for sports is also shared by Hans Hoffman, Principal Architect for Salt Lake-based Hoffman Architects, and Kyle Borchert, Vice President and Project Manager for Salt Lake-based Method Studio, who teamed together to lead the design of this important project, which also proved to be a full-circle, déjà vu-like moment. 


Hoffman and Borchert, ironically, worked together on the design of (then) Utah Valley State College's baseball stadium in 2004 while working for Craig Elliott of Park City-based Elliott Workgroup. It was Hoffman's first sports project, and Borchert's first-ever project as a brand-new intern. Both are huge sports fans: Hoffman said he "will watch any sport" and is a die-hard Utes fan; Borchert played baseball (shortstop) collegiately at Concordia College, a Division III school in Morehead, Minnesota (borders Fargo, ND), as well as club baseball at Montana State during graduate school. 


"Hans and I go way back—it was fun to team up on this project," said Borchert. "Anytime I can combine athletics with architecture, it combines my two loves. It was fun to come full circle—from working with Hans on the UVSC baseball stadium when I was just an intern architect to working together on the soccer stadium now, having been in the architectural field for 20-plus years." 


Hoffman, whose first project upon starting his firm in 2006 was a stadium for the Calgary (now Okotoks) Dogs minor league baseball team (he's currently doing another project for the team), was initially contacted by the Utah DFCM to provide renderings of a possible soccer stadium, which were later used in successful fundraising efforts. Hoffman Architects was then retained to provide cost estimates and develop the programming document, with Method Studio then brought in. 



"We had developed a good conceptual plan," said Hoffman. "When we teamed with Method the concept stayed the same. Teaming with Method was seamless and we tapped into their resources and DFCM experience to push the project forward. I've known those guys for years—they're easy to work with." 


Main Challenges Included Mitigating Adjacent Highway Noise, Narrow Worksite

Bordering the perpetually bustling I-15 highway—an estimated 20 million vehicles annually—posed a couple of primary challenges: mitigating traffic noise and dealing with a razor-thin worksite, while keeping the field open during construction. 


Regarding sound reduction, walls to the north and south were made taller, blocking noise for fans in those areas. “The result is a palpable experience where you immediately go from deafening freeway noise as you walk up to the stadium, to a quiet hum that falls into the background and an ability to hear everything that is going on in the stadium," said Borchert. 


As for the site, little space to navigate between the east-west direction necessitated a long, narrow building, meaning long runs for mechanical ducting and electrical/AV/IT conduit. The orientation also affected seating layout, with it being oriented more vertically than horizontally, which creates a unique viewing experience where you feel like you're on top of the action on the field. Every seat has a great view of the field, another hallmark of this project. 

"I challenge anyone to find a soccer stadium anywhere in the country that has better views than [...] UCCU Stadium—we did our best to capture them," Borchert said.

  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button

A Stadium Worthy of a Growing University, Rising Soccer Programs 

It's no secret that Utah Valley University is experiencing incredible growth—the school is projecting just over 50,000 students in Fall 2025, tops in the Beehive State and an increase of nearly 20% since 2018. This growth requires new buildings and improvements to athletic programs, with UCCU Stadium designed to accommodate a rabid fan base. 


The men's and women's soccer teams currently compete in the Western Athletic Conference—alas, this is their last year in the WAC, with both moving to the Big West Conference starting in 2026-27. 


Fan support for both programs has been stellar. UVU's women's team, which joined NCAA Division I in 2003, ranks 11th nationally in attendance the past four years. The men's program, which became a Division I member in 2009, ranks 14th nationally in attendance. 


Dunn is thrilled with the new and improved amenities at UCCU Stadium, and its long-term impact on not only UVU's programs, but club and youth soccer programs in the region. 


"This rivals anything in (NCAA Division I) sports," said Dunn, who spent over a decade helping develop youth soccer clubs in Utah County. 

The nearly 21,000-SF stadium includes seating for up to 3,000 fans, plus eight luxury suites with eight soft outdoor seats, two indoor seats (10 people per suite) and heaters in the ceiling for cold weather games. 


An MLS-style press box includes a broadcast/PA announcer booth, and a 500 SF media booth with space for 15 people. 


Players will benefit from spacious and stylish new locker rooms that are decked out with all the perks including a player's lounge, training room with hot and cold tubs, along with ample storage. Highlights include custom lockers, rubber flooring in the pattern of a jersey with UVU's wolverine logo in the center, plus an oversized touch monitor for film study and a ceiling that literally looks like the lines of a soccer field. 


Designers were able to add a sizeable 7,500-SF, two-story building on the SE corner that houses concessions, a UVU team store, and restrooms on level 1, and an accessible rooftop party deck on level 2 devoted to students, allowing them to socialize while taking in the game. 


"To me, it's the most underrated portion of the project as it's a great venue to look down onto the soccer field to the north—as well as the softball field to the south)—but it also alleviated a huge need and greatly increases the fan experience," said Borchert.


Interior spaces are lively and fun, with UVU's signature green shining through in various branding hits throughout the facility, including wide cutouts in walls with turf inlays, and a drop ceiling cloud with lighting that mimics the netting in a soccer goal. 


Both designer and contractor raved about the relationship between their teams, and with UVU's athletic department, led by Dr. Jared Sumsion, Athletic Director.


"We assembled a championship team with a team of four guys," said Dunn. "We had a really good culture on this project, top to bottom. The job was awesome—the ownership was amazing; we had a great relationship with Dr. Sumsion. It was just a fun process." 


Hoffman and Borchert agree that the final product exceeds their expectations. 


"It's an awesome place to watch a game," said Hoffman. "Even I was blown away; the design creates an unbelievable atmosphere for soccer where you're right on top of the action." 


"It's such a fun venue—just an awesome way to take in a game." added Borchert, who helped design the Utah State University Maverik Stadium east-side renovation in 2023. He said particular consideration was given to how modern-day fans experience game days, with an emphasis on creating spaces to view the action on the field from various locations throughout the stadium.



"Gone are the days where you sit in your seat all game," Borchert said. "It's about having places where people can congregate and still enjoy the game-day atmosphere. There are 360-degree views with pockets of locations where you can take the game in at a different level."

Just like a good full-circle experience should be.


UCCU Soccer Stadium
Location:
Utah Valley University
Start/Completion:
March 2024/August 2025
Cost:
$21 million
Delivery Method:
Design-Bid-Build
Stories/Levels:
3 + Accessible Rooftop
Square Footage:
20,770-SF Soccer Stadium; 7,464-SF Restroom/Concessions Building
Owner:
Utah Valley University
Owner's Rep:
Frank Young & Kurt Baxter – UVU Facilities; Jared Sumsion – UVU Athletics
Design Team
Architect:
Method Studio (architect of record); Hoffman Architects (design architect)
Civil:
Ensign Engineering
Electrical:
Resolut
Mechanical:
Resolut
Structural:
BHB Structural
Interior Design:
Method Studio
Landscape Architect:
MGB+A Studio



Construction Team
GC:
SIRQ Construction
Concrete:
Cornerstone Concrete
Plumbing:
Gunthers Heating, Cooling, and Plumbing
HVAC:
Comfort Systems USA
Electrical:
STF Electric

Masonry: AK Masonry
Drywall:
Lacem Construction
Painting:
C5 Coatings
Tile/Stone:
JRC Tile & Stone
Millwork:
Artistic Mill
Flooring:
Wall 2 Wall Commercial Flooring (carpet, resilient, athletic & turf flooring), Urbane & Company (sealed flooring)
Roofing:
Progressive Roofing
Glazing/Curtain Wall:
Skyview Glass



By Brad Fullmer October 15, 2025
When Lehi-based Reef Capital Partners (Reef) initially announced plans in 2018 to build a sprawling, estimated $2 billion mega-resort with a championship-caliber golf course on 600 acres covering parts of Ivins and Santa Clara—small towns with just over 15,000 combined residents at the time—it was difficult to fathom what a project of that magnitude might look like. Fast forward seven years, and Black Desert Resort is indeed a shining oasis amidst Southern Utah's famed red rock cliffs, sitting atop an ancient lava field, with buildings strategically carved into the land to produce a resort unlike anything else. "This is the biggest project we've ever done—we feel really good where we are," said Brett Boren, President of Real Estate for Reef, acknowledging the general completion of the $290 million, 806,000-SF resort center, along with significant ongoing work—including a 1,298-stall parking garage, condominiums, and a private water park. As of September, all aspects of the main resort center were open and fully complete, with the hotel celebrating its first official year in business after partially opening in September 2024 as it hosted the inaugural PGA Black Desert Championship October 10-13. The second installment of the tournament—now dubbed the Bank of Utah Championship—is slated for October 23-26, with a third tournament signed for 2026.
By UC&D October 1, 2025
In 2005, Calder Richards Consulting Engineers formed after the merger of two smaller structural consulting firms who, interestingly enough, both started in 1986. Calder Richards has provided a steady structural support for Utah’s built environment ever since. As the firm celebrates its 20th anniversary, UC+D spoke with Managing Principals Shaun Packer and Nolan Balls to look back over the company’s history and celebrate what has helped their firm stand out to deliver solid projects in Utah and beyond. Their responses were edited for clarity and brevity. UC+D: What have been some catalytic moments for Calder Richards since that initial merger? SP: Winning the Talking Stick Resort in Scottsdale, Arizona is the first one. The big reason for the merger between Richards Consulting Group and Calder Consulting was to build a large enough company to go after bigger projects like that.” NB: That was my first project when I was hired straight out of college. We helped design the 17-story hotel and casino, a conference center, as well as parking structures, a central mechanical building, and a pool building. Talking Stick helped get us through the downturn a few years later. UC+D: What have been your key market sectors you all have targeted over the last 20 years? NB: We were breaking into K-12 along the Wasatch Front soon after the Talking Stick Resort and it’s been our bread and butter since then. SP: Absolutely, but I credit our firm for always adapting to the current environment. We’ve been fortunate to do so much K-12, but we used to do a lot of office work, and now we are working on conversions like the Ebay Headquarters to CTE/Innovation Center for Canyons School District as the market has shifted away from commercial office. UC+D: Schools have certainly evolved over the last 20 years, how has your work as structural engineers evolved? SP: We are seeing more creative design on the architectural side, certainly. We see many more two-story designs; more windows and daylighting. But we’re utilizing more powerful tools and continually building our understanding of the structural materials that are in use more than ever—tilt-up concrete, steel columns and beams, especially—to be the architect’s trusted partner. NB: Schools have definitely changed, and we’ve had better experience in helping projects move forward successfully when we are involved earlier in the design process. As we got involved early on in West High School’s schematic design, we were able to provide structural solutions and options to accommodate the architects’ design intent. UC+D: How has company growth changed Calder Richards? SP: It’s certainly changed the number of people in our office. We started with around 10 people when we merged, and today we have 27. But we often say that we don’t want to grow just to grow—we want to grow sustainably. We don’t lay people off when works slows down, and we have an expectation that sometimes there will be overtime work, and other times you may be waiting for our next project to begin.
By By Taylor Larsen October 1, 2025
Nested in the middle of the University of Utah (U of U) campus sits the aptly-named Impact & Prosperity Epicenter, the second living learning community (LLC) project designed on campus by Los Angeles-based Yazdani Studio of CannonDesign. After nearly a decade since their first LLC project, the award-winning Lassonde Studios (UC+D’s 2016 Most Outstanding Public Building over $10 million), Mehrdad Yazdani, the design firm’s Principal and Studio Director, said their work on a sequel was an exciting prospect for the firm, and enlisted Salt Lake-based MHTN Architects and Okland Construction to serve as the respective local architect and general contractor. Today, the Epicenter serves as a striking piece of architecture and construction, one whose curvilinear shape asks users and visitors plenty of questions. But moving from idea to execution has been a work in progress. One query from Yazdani stood out as it relates to students and the built environment, and helped begin the journey to create the Epicenter: “How does your living environment as a student impact your success as a student and as a changemaker?” A Project for an Evolving Campus Katie Macc, CEO of the Sorenson Impact Institute, said LLCs like the Epicenter and Lassonde Studios next door have been massive steps forward in advancing entrepreneurship and social impact. But both play a major role in creating “college town magic”—a phrase coined by University President Taylor Randall that invokes a vibrant campus where students can find community and have one-of-a-kind experiences. With more on-campus student housing in the works, the state’s flagship university is hoping to shed the “commuter school” label and deliver a level of desirability that matches the resources students commit to higher education. “There is some soul searching going on across university campuses,” said Macc of the challenge at hand. “We have to be convincing that going to college matters.” She said overall university enrollments across the nation are decreasing as students grapple with tuition costs, COVID and its isolating aftershocks, and a different perspective on higher education. Universities are no longer a place where students come to learn what they couldn’t learn elsewhere—remote learning and the internet have opened a fissure in that idea that will never close. Instead of that educational transaction, being at a university must include building community and creating in-person experiences only available on campus. Macc said that the Epicenter helps steer the campus experience toward the future, with design goals to create a base of operations for two changemaking organizations and a living and learning home for 778 students. The three-story commercial portion of the building, known as the “Changemaker Pavilion”, includes office space for The Center for Business, Health, and Prosperity (second floor) and the Sorenson Impact Institute (third floor). While each organization has a different focus, both are firmly invested in helping students access and create the resources needed to change the world. Each entity works hand-in-hand as owners of the Epicenter to host events and “create a full spectrum of ways for students to get involved,” said Chad Salvadore, Chief Financial Officer for the Sorenson Impact Institute. “We’re dialing in the programming to energize the student body,” said Salvadore of the work done at the Epicenter. With over 60 majors represented among the 778 students who live there, he said that the diversity of students is less a reflection of their chosen major and more a desire to reside in a space built for students to work their entrepreneurial muscles. “Living here is a mindset—you can engage across many different paths you choose.”
By Brad Fullmer October 1, 2025
Over the course of its 40-year history in Utah, WSP's Salt Lake office—originally founded as Parsons Brinckerhoff in 1985—has morphed from primarily a transportation design firm to one that successfully operates in multiple civil engineering markets. The results of WSP's transformation the past decade into a more diverse outfit speak for themselves, with the 128-person Salt Lake office (with locations in Cottonwood Heights and South Jordan) posting three consecutive years of revenues over $50 million, including a record $70.1 million in 2023, and a robust $59.9 million in 2024—good for the No. 2 ranking in UC+D's 2025 Top Utah Engineering Firms rankings.
By Taylor Larsen October 1, 2025
Lucio Gallegos vividly remembers the workforce development meetings he attended during his time at Ogden-Weber Tech. These career and technical education (CTE) discussions consistently focused on one thing: young people were not entering construction, and the industry needed a new approach to attract them. Gallegos recalled one member of the workforce development team, a training director with a prominent general contractor, saying, “We have been trying this for over 10 years, screw it, we’re just gonna hire them.” The Long Road Those conversations occurred nearly 10 years ago, and workforce development concerns continue to permeate the industry. The National Center for Construction Education & Research estimates that 41% of the construction workforce will retire by 2031, leading to potential gaps in skill and safety and decreases in productivity and project quality. While stakeholders have aligned on the overall goal of providing students a foundation for future success through career development, the means to achieve the ends were seemingly at odds. High schools, trade schools, colleges, and private industry took different paths to achieve their goals, with some moving in opposite directions. “I’m gonna be honest with you,” Gallegos recalled one school administrator saying, “If I promote what you’re telling me to get them over to the tech college, I lose head count. And then I lose teachers. I can’t have a school without teachers.” Jobs that took away student learning experiences, according to federal guidelines and child labor laws, made the idea a non-starter. However, after years of lobbying the Utah Legislature for a compromise between industry and education, H.B. 055, passed in 2023, provided a catalytic change in how younger people can engage with construction and other industries. High school students could participate if they were involved in a school-sponsored work experience and career exploration program. Private industry finally had the compromise it wanted. It was time to act. Big-D Charts New Path Gallegos, now the Workforce Development Manager from Big-D, joined the company in 2023 with the express purpose of creating a program that fit within the new guidelines. Gallegos said he sees career development through the lens of the immigrant experience, one he knows personally as a Mexican immigrant with a father who worked in commercial construction. “I was 9 years old and busting pins out of concrete forms with a hammer that was as big as I was,” he laughed. “I’ve got the cliché immigrant story.” That story has a theme familiar to many immigrant families, he said, one where parents say, “I want my kids not to have to work as hard as I do. I want them in school.” Add to that, it’s a law—children must attend school. Gallegos was unfazed by those obstacles. As he began planning how Big-D’s internship program would operate, he knew that engagement had to start at the elementary school level and build on personal relationships between private industry, school administrators, students, and their families to succeed. “We want to be the solution, not the obstacle to get into this industry,” said Gallegos. So Big-D removed the barriers. Students can still attend school, work towards graduation, and be available in the afternoon for sports, extracurricular activities, and the high school experience. But working was another significant part of the immigrant experience, Gallegos said, and internships needed to be paid to alleviate the family concerns. “We asked what we would pay somebody fresh out of high school who worked at Big-D,” Gallegos said. Interns have earned those same wages ever since.
By Brad Fullmer October 1, 2025
On January 2, 1957, Gene Fullmer, a scrappy, underdog fighter from West Jordan stunned the boxing world with a 15-round unanimous decision over the legendary Sugar Ray Robinson at New York’s fabled Madison Square Garden. Fullmer captured the world middleweight championship and established himself as one of the best pound-for-pound boxers during the late 50s and early 60s. Since then, the Fullmer name has been synonymous with boxing in Utah, with brothers Gene, Jay, and Don establishing the Fullmer Brothers Boxing Gym in 1978, and offering free boxing instruction and life mentoring to thousands of youths—carrying on a tradition they learned from their trainer, Marv Jenson. Their legacy of community giving will live on in the new Fullmer Legacy Center in South Jordan, a 16,500-SF facility that will serve as a permanent home to the boxing gym—after years of bouncing around to various temporary facilities—along with a museum, snack bar, and gift shop. “The Fullmers are the first family of boxing in the state of Utah—that’s well understood,” said Dave Butterfield, a founding board member of the Fullmer Legacy Foundation. Butterfield served as Chairman of the Board from June 2016 to early 2025 and was influential in helping raise money—nearly $6 million via donations to date, which includes $2 million from the Utah Legislature. Project Driven by Vision to Find a Permanent Home for Fullmer Brothers Gym It was Jay Fullmer who led the charge to teach boxing in the community. By 1978, the Fullmer Brothers Boxing Gym had formally opened at the Butterfield farm chicken coop in South Jordan, recalled Larry Fullmer, Don’s oldest son and the man who spearheaded the efforts for the Fullmer Legacy Center. From there, Larry said the facility moved to Riverton Elementary, an old church house in West Jordan, a sugar factory, a former fire station, and the Salt Lake County Equestrian Park in South Jordan, where it had resided since 2011. When they got word that Salt Lake County planned to transfer ownership of the park to Utah State University, Fullmer knew they needed to find a long-term home for the boxing gym. Fullmer met with Butterfield and Robert Behunin—who at the time was a Vice President with Utah State University—in 2016 and told them he just wanted a “tin shed of our own” for boxing. Behunin countered by saying, “If you want people to donate money, you need something better than a tin shed!” They quickly formed the Fullmer Legacy Foundation (FLF), and by 2018, the wheels were in motion on a building. Doc Murdock, a long-time trainer at the gym, connected Larry with his former roommate at Brigham Young University, Vern Latham, who is a Principal at Salt Lake-based VCBO Architecture. VCBO offered pro-bono services initially while helping FLF put together an RFP, while North Salt-based Gramoll Construction provided value engineering and other services in an effort to get the project launched. Larry expressed sheer gratitude for the contributions of both firms in helping make the project a reality, especially for many generous donations from various foundations and individuals. “[VCBO] believed in us early on and did our first phase of planning at no charge—they have been amazing and so professional to work with,” said Larry. “Gramoll helped us get the budget done as tight as it could be. This project had the absolute tightest budget. We met weekly with architects and the general contractor to see the progress—I’ve never seen such an amazing process. Construction started in November ’23, and every time I would come to the jobsite in the first six months, I’d get emotional.” “We leaned on our relationships with contractors for flooring, ceiling, tiles, donated furniture and got deep discounts and a lot of in-kind donations,” said Phil Haderlie, Principal-in-Charge for VCBO. “To me, the story of this project is the grassroots effort of people seeing the value—this is something that came from their heart. It will have a long-lasting impact on the community.”
By Brad Fullmer October 1, 2025
The first season is in the books for the Salt Lake Bees in its spectacular new home—the Ballpark at America First Square, the exciting new heart of Downtown Daybreak and certainly one of the premier Triple-A stadiums in the country. "It's a really cool stadium—the field looks so good!" gushed Eric Barton, Project Director for Salt Lake-based Okland Construction, while surveying the spacious 280,000 SF, 6,500-seat (8,000 capacity) ballpark. Barton said his team faced an extremely difficult construction schedule with the mandate the project had to be sufficiently ready for Opening Day 2025 on April 8, less than 18 months after the formal October 20, 2023, groundbreaking. Barton said Okland knew it was going to be a grind, with long hours and tight windows to get various milestones accomplished. "When we bid this to our trade partners, we had them bid it with the expectation of it being six days a week," he said. "We want not only your best guys, but you have to be adaptable to the plan. It was gangbusters from the start.” Up to 300 workers were onsite during peak construction activity, requiring meticulous coordination throughout. Okland even brought in Fred Strasser, a legendary project director who came out of retirement to shepherd the project through. "Fred is the genius behind getting this whole thing done," said Barton. The project was designed by Salt Lake-based HOK, who worked closely with the owner, Sandy-based Larry H. Miller Real Estate (LHMRE) and Miller Sports + Entertainment (MSE) to bring about a project that would add even more buzz to its wildly popular, 4,000-acre master planned Daybreak development in South Jordan, making it a true entertainment destination. The design weaves together best-in-class baseball experiences with year-round public amenities, including a recently opened Megaplex theater, a performing arts center, a large amphitheater, along with retail, restaurants, and apartments, with buildout continuing through 2027. Walking paths and open spaces create natural connections between The Ballpark and the surrounding neighborhood, making the area an iconic community asset and a true sports and entertainment district. Downtown Daybreak is slated to host more than 200 annual events—including the Bees’ 75-game regular season. Supporting this entertainment destination, the venue’s prominent location just off the Mountain View Corridor freeway makes it highly visible to passing traffic while providing easy access. The stadium is also connected to multiple transportation options, easily reached by walking, biking or light rail across the Wasatch Front, and by car from the new freeway corridor. The Ballpark site drops 20 feet from the loading dock to the plaza, managed through terraced spaces that echo the region’s mining heritage. Though the slope stays gentle at under 5%, carefully placed stairs and planters make walking comfortable while honoring the industrial past. The center field main entrance connects to light rail, while a formal plaza at home plate serves as a second entrance, primarily for VIP access. The street design follows Daybreak’s established standards for lighting and tree spacing. Bike racks at the light rail station and plaza make cycling to games convenient. Utah’s Landscape Shapes Design The Wasatch Mountains, visible from every angle of the ballpark, directly influenced the ballpark's design. Throughout the venue, carefully planned viewpoints frame these mountain vistas. The structure resembles this mountainous setting in its form, transitioning from solid brick and concrete at its base to lighter materials—metal and expansive glass—as it ascends. Working with Kansas City-based architectural metal fabricator Zahner, HOK and MSE created a distinctive facade using perforated metal panels that suggest Utah mountain peak silhouettes from Ben Lomond Peak in Weber County to Mt. Nebo, the southernmost and highest mountain in the Wasatch Range of Utah. These panels transform into a glowing display at night, serving as a lantern on The Ballpark’s ‘front porch’ and welcoming visitors. This connection to Utah’s landscape flows throughout the site. Angular planters guide visitors along pathways, while public spaces are arranged in terraces that echo the mountainside. The copper colors and stepped surfaces of the nearby Kennecott Mine inspired the ballpark’s materials and layout. Inside, the decor features warm copper, gold and honey tones, with textured materials that blend the natural landscape with the Salt Lake Bees’ team colors.
By Brad Fullmer October 1, 2025
Horrocks CEO Bryan Foote (left) shakes hands with Matt Hirst, former President/CEO of CRS Engineering & Survey. Horrocks acquired CRS a year ago in a move that has proven to be a seamless fit for more than 60 CRS employees.
By UC&D August 1, 2025
Nathan Goodrich
By Brad Fullmer August 1, 2025
Paul founded Paulsen Construction in 1925 after immigrating from Norway 16 years prior. Sprague Library in Sugar House was originally built by Paul, and then restored nearly 100 years later, led by current President John Paulsen.